Phase I

DISCOVER THE new TENANT CENTERED AMENITIES

From the addition of a new restaurant/bar concept to inviting on-site amenities like the new fitness center, fully equipped bike lockers and showers — discover select upgrades at One Nashville, and stay tuned for more coming soon!


closing out 2019 with a bang

November 2019

Construction on Printers Alley and the building amenities is beginning to wrap up, with Tenants able to start 2020 off with a brand new fitness center, new locker rooms and a place for their bike within One Nashville. This month,

  • Bike racks were delivered and installed

  • Lockers for the bike room/fitness center were delivered and installed

  • New equipment for the fitness center was delivered

  • Shower doors, lighting and counter tops have been installed in the new locker rooms

  • Cement for the retail patio off Printers Alley has been poured

 

printers alley gets a little brighter

OCTOBER 2019

Exterior construction took a brief pause while riskrock visited Printers Alley to paint a new mural, bringing the main focus on the interior improvements. Current progress includes:

  • Flooring for the fitness center was installed

  • Bathroom and shower tile was completed, followed by a fresh coat of paint on the walls and ceiling

  • Main corridor drywall was patched and painted

  • Ceiling installation for the new bike room was completed

  • Exterior patio walls in Printers Alley have been formed and storefront doors have been installed and protected

Special thanks to Risk and 2:32 AM Projects for the cool new addition to Printers Alley.

 


Construction Begins on Printers Alley

September 2019

Construction is well underway with a focus on interior demo and framing of the new entry from Printers Alley, the new locker room showers / bathrooms and added bike locker. Current progress includes:

  • Removal of exterior wall leading into Printers Alley and sheathing with a temporary entry were installed

  • Removal of the existing generator to complete electrical shutdown and framing of the exterior wall with a rough opening for the new entry door from Printers Alley

  • Blocking for the new bike locker complete and bike racks are on their way

  • Installation of underground plumbing and framing for the new locker room showers/bathrooms